IEPS currently expects that in the order of 25 to 29 months will be required, once internal approval to proceed is received, to advance the project through design, construction, commissioning and into operations.

Under the current schedule, IEPS anticipates that approximately 15 months will be required to reach Final Investment Decision (FID).This will include an initial 9 months to complete Front End Engineering and Design (preliminary design), carry out the initial stakeholder engagement process, and finish the filings for regulatory review. The receipt of the required regulatory approvals is expected to require an additional 6 months.

Post a positive FID approximately 10 to 14 months is expected to be required to complete construction and begin commercial operations.